Transportation of towers to the Szymankowo Wind Farm

Contrast
Font size - A +

Transportation of towers to the Szymankowo Wind Farm

The works in the Szymankowo wind farm site are under way.

The construction started in March this year and is scheduled to be completed in February 2021. So far all foundations have been completed – each with the diameter of 20 meters, built using 70 tons of reinforcement and 530 m3 of concrete. Two sections of the first Baltic Operator tower have been delivered. The next ones will be transported soon. The turbines are supplied by Siemens Gamesa. The Szymankowo Wind Farm will be composed of 11 wind turbines with the total capacity of 38 MW.

The project is executed with PBDI, Siemens Gamesa and Bilfinger.